Sl. No
|
Description
|
Yes/No/NA
|
1.
|
Is the bill in prescribed format and in “ORIGINAL”?
|
|
2.
|
For the First and Progressive bills, are the original agreement with enclosures and Performance guarantee available.
|
|
3.
|
Is agreement no. mentioned on the bill?
|
|
4.
|
The conditions, if any, mentioned in the TC minutes and draft agreement complied
|
|
5.
|
Is the allocation furnished in the bill in accordance with the sanctioned estimate?
|
|
6.
|
Is the fund certification and work register posting furnished in the bill?
|
|
7.
|
Is the currency for the period available?
|
|
8.
|
Is Measurement Books / IR-WCMS enclosed for billsfor works contract?
|
|
9.
|
Are the necessary certificates, Test Check and signatures of the executive staff and officers obtained on the Measurement Books?
|
|
10.
|
Is the date of Test Check mentioned in the bill?
|
|
11.
|
Is the signature of contractor obtained on the bill tallies with that in the original agreement?
|
|
12.
|
Is the executed quantity within the agreement quantity?
|
|
13.
|
If not, is the rider proposal enclosed for variations duly concurred by finance, if applicable
|
|
14.
|
Is deviation statement enclosed?
|
|
15.
|
Does the final bill amount tally with the final rider proposal?
|
|
16.
|
Is Final variation statement, No Claim/No due Certificate enclosed for final bill?
|
|
17.
|
Is the final rider Agreement along with the concurrence and sanction of the competent authority enclosed with the final bill?
|
|
18.
|
Does necessary sanction of the competent authority exist for rider agreement?
|
|
19.
|
Is the work order enclosed for Zonal Bills? If date of commencement is before the date of issue of work order, has it been regularised?
|
|
20.
|
For quotation bill, is necessary sanction of the competent authority been obtained?
|
|
21.
|
For huge variation in work order amount, has competent authority's sanction been obtained?
|
|
22.
|
In case of excess over estimate, is the certificate regarding cost escalation and other than cost escalation furnished in the bill?
|
|
23.
|
PAN No. & TIN No of contractor has also been furnished on bill
|
|
24.
|
Completion certificate for performance guarantee release is enclosed?
|
|
25.
|
completion of maintenance period/warranty if applicable, No due/No claim certificate enclosed for SD release?
|
|
26.
|
Whether penalty imposed is as per the agreement & after approval of competent authority?
|
|
27.
|
If Recovery is made towards additional security deposit, additional PG or any other penalty, approval of competent authority is obtained to refund the same?
|
|
28.
|
Important documents such as Guarantee / Warranty Certificate, Test Certificate, Inspection Report / Performance Guarantee bond / Indemnity Bond etc., should have been furnished to the Consignee by the contractor.
|
|
29.
|
Ensure all the TDS applicable are deducted. Ex. TDS under 194Q, 194C, 194J of The income tax act 1961 and TDS under GST act.
|
|